Project Schedule
.jpg)
Phase IA will consist of the sitework modifications, which will enhance the bus drop-off loop and the parent queuing loop. It will also encompass the construction of the campus' new central energy plant. Interior demolition of both the first and second floor within the building's south wing will also commence over the summer to allow for a timely turnover of Phase IB.

PHASE IA
SUMMER SITEWORK
New Central Energy Plant,
South Wing Demolition
Phase IB will consist of the interior renovations and enhancements of the building's south wing first and second floors. The enhancements will include new classroom layouts, all new interior finishes and building envelope improvements, which include new roofing, new windows and exterior paint.

PHASE IB
South Wing Interiors,
First and Second Floors
& Reroof
Phase IIA will consist of the demolition and renovation to the north wing first and second floors. The enhancements will include new classroom layouts, all new interior finishes and building envelope improvements, which include new roofing, new windows and exterior paint.

PHASE IIA
North Wing Demolition,
Interior Renovations
and Reroof
Phase IIB will consist of expanding the facility's existing kitchen and converting it into a full kitchen in lieu of the obsolete warming kitchen.

PHASE IIB
Complete North Wing
Interior Renovations,
Begin Kitchen Expansion
Phase III will consist of the interior renovations and enhancements to the existing cafeteria space, which will include new ceilings, lights, flooring and paint. They will also include a new stage and modified points of ingress and egress. The lobby will be receiving enhancements during this phase as well, which include the refinishing of the beautiful terrazzo flooring.